How To Do Pile Driving With Percussion Method

There are several types of pile driving method in the piling construction, type of pile driving method used is depending on the condition of soil and location of the site. However, different piling machine will be used with different pile driving methods too. The specification for pile driving mentioned below is generally recommended for pile driving of prestressed spun concrete piles by using percussion method. Engineers may be required to modify some of the clauses to suit requirements of different site conditions.

How To Do Pile Driving With Percussion Method

1) Joints

The bending strength of a joint between two lengths of pile shall be equal or more than the bending strength of the concrete shaft. When two lengths of pile are jointed, the end plates must bear over their complete areas. The two end plates are then welded along their entire periphery with weld size as specified.

1.1 Welding of Joints
All welding shall be carried out in accordance with the requirements of B.S.5135:1974 - Metal-Arc Welding of carbon and carbon-manganese steel.

1.2 Tests for Approval of Welders
Welders shall be qualified in accordance with the requirementsof AWS Code D1.1. Only welders who pass the qualifying tests for the type of weld specified shall be employed on the Works.

1.3 Examination of Welds
Butt welds between the end plates of the joints shall be tested using magnetic particle or dye penetrant test methods. Copies of these test records and reports shall be furnished to the Engineer.

Where such examination reveals defects in the welds, the joints shall either be rejected or repaired. If repeat tests show the weld to be still defective, the joint shall be rejected. The defective weld shall be removed, replaced with a fresh weld and re-examined.

For the purpose of this Clause, cracks, leaks, laminations, lack of complete fusion, undercutting or reduction in wall thickness adjacent to the weld shall constitute a defect.

2) Pile Driving by Using Percussion Method

2.1 Pile Hammers
Shall be of size and type able to deliver consistently an effective dynamic energy suitable to the piles to be driven and the material into which they are to be driven. Hammers shall be provided with proper driving helmets suited for the piles. Any indication of collapse of hoses, tripping of hose lining or any erratic action of the hammer shall be cause for immediate shutdown until the problem has been corrected.

Pile hammers shall be operated at the full rated efficiency and capacity and in the manner specified by the manufacturer, except as directed otherwise by the Engineer, or noted herein below under Reductiono of Hammer Energy.

When a steam or air hammer is used for driving any type of piles, both the volume and pressure of steam or air recommended by the manufacturer of the hammer shall be maintained at all times to ensure full energy of the driving blows. Before pile driving is started, the Piling Contractors shall provide written certification to the Engineer that the pile hammer, compressors and valves have been inspected and found to be in good working condition.

2.2 Reductiono of Hammer Energy
When the pile is set in a pre-jetted or pre-drilled hole or when the point of a prestressed concrete pile is passing through soft soil so that there is little or no resistance to penetration of the pile, there is a possibility that longitudinal tensile stresses may be set up in the pile shaft by the elastic shock waves travelling up and down the pile. For such driving conditions, the length of stroke of the hammer shall be reduced. Failure of the piles due to longitudinal tensile stresses caused by excessive driving shall be the Contractor’s responsibility.

2.3 Pile Cushion Block
The heads of all prestressed concrete cylinder piles shall be protected with a soft wood cushion block at least 15 cm thick to effectively and uniformly distribute hammer blog energy. The block shall be composed of layers of 20mm hi-grade marine plywood or approved equal, and of such dimensions as to completely cover the concrete cross-section of the pile. The cushion block shall be inspected periodically during driving and no driving shall be done with a block that has been unduly worn and compressed with use. Cushion blocks must be replaced when compressed to 1/2 their original thickness, when badly worn or when burning.

2.4 Driving
The piles shall be driven to the driving resistance or tip elevation as determined by the Engineer from pile load tests. The maximum allowable variation at the butt end of the pile shall be 150mm in any direction from the location shown on the Drawings or as directed by the Engineer. Any variation beyond these limits shall be allowed or rejected at the sole discretion of the Engineer.

3) Cutting Off and Capping Piles

Tops of foundation piles shall be embedded in the concrete footing or pile cap for a minimum depth of 75mm (measured at center line of pile). When the top elevation of a pile is below the elevation of the bottom of the cap, the pile shall, if approved by the Engineer be built up from the butt of the pile to the elevatioon of the bottom of the cap by an approved method. The cuts shall be made accurately in clean, straight lines; care shall be exercised to avoid damaging the remaining pile and to ensure full bearing between the footings (or pilecaps) and piles.

Archived under Pile Driving, Piling Comments

How To Drill Bored Pile

Usually bored pile is used for those tall buildings or massive industrial complexes, which require foundations which can bear the load of thousands of tons, most probably in unstable or difficult soil conditions. The method of drilling bored pile is different from RC Square pile or spun pile which are using driving method, the piling machine to be used will be different too. Bored piling works required specialist bored piling contractor to follow up instead of hiring general piling contractor. There is a simple step-by-step method on how to drill the bored pile in construction site.

How To Drill Bored Pile

1) Adjust the piling machine on the pile axis and haul with the auger to the drilling place.
Adjusting The Axis

2) Start drilling until the auger is filled.
Drilling Bored Pile

3) Return from the drilling level to the top of the pile hole.
Returning

4) Swing to the uploading area.
Swing

5) Unload the dirt in the unloading area.
Unloading The Dirt

6) Swing back to the top of the hole.
Swing Back

7) Repeat steps 2 to 7 until the pile is completely drilled. Relocated the machine and start steps 1 to 8.
Moving

8 ) Start erecting rebar cage using a crane.
Rebar Cage

9) Use funnel for dry method and tremie for wet method. Start pouring the concrete and finish the pile.
Tremie

Video On How To Drill Bored Pile

Archived under Bored Pile, Piling Comments (1)

What Is Bored Piles

Bored pile is another type of reinforced concrete pile which is used to support high building which has heavy vertical load. Bored pile is a cast-in-place concrete pile where the bored piles have to be cast on construction site, while other concrete piles like Spun Pile and Reinforced Concrete Square Pile are precast concrete pile which they’re cast in the factory.

Normally bored piling has be to carried on those tall buildings or massive industrial complexes, which require foundations which can bear the load of thousands of tons, most probably in unstable or difficult soil conditions. Bored piling is cast by using bored piling machine which has specially designed drilling tools, buckets and grabs, it’s used to remove the soil and rock. Normally it can be drilling into 50metres depth of soil. The advantage of bored piling is its’ drilling method, little vibration and lower noise level.

Bored Piling2

The drilling method is depending on the condition of soil, piling contractor has to do soil investigation and decide which drilling technology has to be carried on. Piling contractor decide the correct drilling technology and minimize disturbance of the surrounding soil. For cohesionless soils such as sands, gravels, silts etc, whether it’s under the water table or not, the pile bore hole must be supported using steel casing or stabilizing muds such as bentonite suspension. After these, reinforcement bar will be put into the bore hole and concrete will be poured into the bore hole.

Bored Piling

Bored piling is popular to be used in construction as a foundation especially for bridge work and tall building as well. Bored piling work has to be done by specialist bored piling contractor, normal piling contractor can’t be done without experience and knowledge about bored piles.

Archived under Bored Pile, Piling Comments

How To Produce Super Strength Pile (SS Pile)

SS Pile or Super strength pile is a type of precast concrete piles, which mean the SS pile will be produced in the factory and delivered to construction site if there is a need. SS Pile is slightly different compare with other concrete piles, SS Pile has a widen radius and it can supports more loads from structures with fewer number of points. There is two types of stressing of tendons, which is post-tensioning and pre-tensioning, while SS Pile is using prestressing or pre-tensioning. Pile which uses prestressing is to strengthen the strengh of pile, or prevent crack and improves its’ strength so that the pile can carries more load.

Procedure and Sketch of How To Produce Super Strength Pile (SS Pile)

1) PC Bar Cutting and Heading

PC Bar Cutting and Heading1

2) Cage Forming

Cage Forming

3) Joints Setting

Joints Setting3

4) Concrete Placing

Concrete Placing4

5) Concrete Batching

Concrete Batching5

6) Prestressing

Prestressing6

7) Spinning

Spinning7

8) Steam Curing

Steam Curing8

9) Demoulding

Demoulding9

10) Autoclaving

Auto Claving10

These are all the steps of how to produce a SS Pile. All the procedures must be followed exactly and done it clean and neat. Safety protection must be carried on for workers who involved in the process of producing SS Pile. After the SS Pile has been done, it will be handled and stored in the factory or yard and ready for delivery.

Archived under Piling, Super Strength Pile Comments

How To Handle And Store Pile

Pile can be done in precast or cast-in-situ, cash-in-situ pile which is casted on the site, while precast pile is casted in the factory and deliver to construction site. This article will be teaching you how to handle and store the precast pile after it has been casted in the factory. Basically this article is writing about handling and storing hollow section pile such as Super Strength Pile (SS Pile). It has several steps need to be followed.

Diagram-1A

Diagram-1B

Diagram-2

Procedures Of Handling and Storing Piles

1) Two point lifting position to be pitched at 0.2 x L distance from the pile ends (Diagram 1a as above). Alternatively, lifting from the pile ends is to be executed with the following controls :-

i) No jerking movements by the crane.

ii) Crane must be stationary.

iii) Vertical lifting rate at slower pace.

iv) Boom of crane to be swung at minimum rate of movement.

v) Piles are to be carried one at a time.

vi) Wire ropes are to be capable of carrying the load.

vii) Free rotation of the top swivel is to be ensured (Diagram 2 as above).

viii) Wire ropes are to be inclined at least 45 degree acute angle with the pile body. (Diagram 2 as above)

ix) Only PPDC verified / authorized hooks are to be used.

x) Two flat M.S. plate hooks are to be used at cross fin shoe ends or circular / torus hooks for conical shoe ends.

xi) Stoppers are to be put at both sides of the piles and fastened to be ground. (Diagram 1b as above)

2) Lifting from one end for pitching is at 0.2 x L. Pile is to be fastened in such a way to prevent slipping (multiple loop grip tie) with the following controls :-

i) No dragging along ground.

ii) Lifting rate at slower pace.

iii) Lifting piles from the ground is to be done at the open-ends with “C” hook.

iv) Nothing must be below the pile at transfer.

3) Refer to diagram 1a and 1b above for storage details.

i) Piles are preferably to be stored according to their respective lengths.

ii) Spacers of 2″ x 4″ hardwoods are to be placed at 0.2 x L from both ends of the piles and in between the 2 layers of piles.

iii) Preferably the ground is levelled and compacted with a 100mm thick bed of 20mm aggregates.

Handle SS Pile

Archived under Super Strength Pile Comments